The PMBOK processes are:
Project planning includes:
Initiation → Planning → Execution → Control → Closure
★ Must-know
📌 The project triangle balances scope, time, and cost or budget, so changing one constraint can affect the others.
Further detail
Scope defines what is delivered, time when, and cost for how much
★ Must-know
📌 A WBS should follow the MECE criterion: tasks must be mutually exclusive, with no duplication or overlap, and collectively exhaustive, including all necessary work.
📌 A work package is sufficiently decomposed when it is clear enough to estimate, assign, and schedule.
Further detail
The course uses a maximum of two subdivisions of the project for simple WBS presentations, while the final palace WBS contains levels 1, 2, and 3 with an X.Y.Z coding scheme.
The palace WBS includes:
MECE: Mutually Exclusive, Collectively Exhaustive
★ Must-know
Further detail
📌 Experts, subcontractors, or suppliers provide estimates of work content, activity duration, and cost, unless the project team provides those estimates itself.
📌 Mario offers excellent-quality Jacuzzi installation for 8 days and 15.000€, whereas Wario offers mediocre quality for 10 days and 10.000€.
📌 An activity with several predecessors can start only after all of its predecessors have been completed.
A project network shows precedence, whereas a schedule shows timing
★ Must-know
📌 Any delay in an activity on the critical path delays the entire project.
Further detail
For the sanitation-facility example, activity C can start in week 5 because it requires completion of activity B, which lasts 5 months in the listed example.
For the Milwaukee air-pollution-control example, the critical path is A → C → E → G → H and the project duration is 15 weeks.
Delay on the critical path → delay to the entire project
★ Must-know
Evaluating a project plan requires checking schedule feasibility and evaluating schedule performance against the project deliverables.
The initial palace plan finishes in 34 days but exceeds the 100.000€ budget by reaching a cumulative cost of 105.000€.
📌 Using lower-cost suppliers can reduce the budget, but it may also reduce quality or change the project plan’s feasibility.
Further detail
Meeting the deadline can require higher cost or lower quality
★ Must-know
📌 Choosing cheaper suppliers can reduce the planned project cost, but it may also involve lower quality and greater execution risk.
📌 A project plan must be evaluated against its budget, deadline, and required quality before execution is authorized.
Further detail
Cheap suppliers reduce planned cost but can increase quality and execution risks.
★ Must-know
Project control monitors execution by comparing real time and true cost with the planned estimates and by identifying deviations that threaten the project objectives.
The resulting project performance missed the budget, exceeded the deadline, and used low-quality materials.
Further detail
Waluigi’s masonry was planned at 5,000€ per wall but required 12,000€ per wall in reality, while the work still took 2 days per wall.
Wario’s plumbing was planned to take 10 days but required 20 days in reality, while its true cost remained 10,000€.
Unforeseen difficulty → higher costs, delays, and failure to meet deliverables.
★ Must-know
Revising the WBS can split Yoshi’s single foundation activity into separate activities for the palace slab and the Jacuzzi slab.
A revised schedule can sequence the palace slab, masonry, Jacuzzi slab, plumbing, roofing, and decoration so that the project remains within its constraints.
Further detail
Split the activity, estimate each part, then reschedule the work.
★ Must-know
📌 When an execution problem occurs, the project team can either revise the project execution or revise the project plan.
📌 A change during execution must be assessed for its effects on budget, deadline, quality, and project deliverables before it is accepted.
Further detail
Revise execution when the work changes; revise the plan when the project constraints change.
★ Must-know
📌 If an early stage of project management is poorly performed, subsequent stages are likely to fail; for example, an incorrect WBS prevents optimal scheduling.
Further detail
Plan → execute → control → revise.
★ Must-know
The suggested management-plan chapters are:
The project team should define the project and its reasons, identify deliverables, scope, and stakeholders, build the WBS, create an initial schedule and network, allocate responsibilities, and prepare a first budget.
Further detail
📌 The project document must include the project charter and a bibliography arranged alphabetically according to APA style.
| Dimension | Question | Palace example |
|---|---|---|
| Scope | What will be delivered? | High-quality palace with a Jacuzzi and dressing room |
| Time | When must it be completed? | One month |
| Cost | What is the budget? | Maximum 100.000€ |
| Supplier | Quality | Time and cost |
|---|---|---|
| Mario | Excellent | 8 days; 15.000€ |
| Wario | Mediocre | 10 days; 10.000€ |
| Luigi | Excellent | 2 days per wall; 10.000€ per wall |
| Waluigi | Mediocre | 2 days per wall; 5.000€ per wall |
Test your knowledge on Project Planning and Scheduling with 11 multiple-choice questions with detailed corrections.
1. Which sequence lists the project management processes presented in the PMBOK framework used here?
2. A project manager is preparing a plan by identifying deliverables, activities, resources, estimates, and the schedule before assessing the plan itself. Which project process is being performed?
Memorize the key concepts of Project Planning and Scheduling with 11 interactive flashcards.
What are the five PMBOK project management processes presented?
Project initiation, project planning, project execution, project control, and project closure.
What activities are included in project planning?
Setting deliverables, defining activities and resources, obtaining estimates, scheduling, and evaluating the plan.
What three constraints does the project triangle balance?
Scope, time, and cost or budget.