★ Must-know
A decision tree starts with one decision node, branches into possible outcomes, and continues through further nodes representing additional possibilities.
In a decision tree, the square marks the point where a decision is made and the circles mark the points where outcomes are realised.
Further detail
★ Must-know
Decision trees are easy to understand and interpret, require minimal data preparation, and force decision-makers to consider multiple possible outcomes.
Decision trees may become too complex, may rely mainly on expectations that produce unrealistic outcomes, and may narrow attention to critical decisions and objectives.
Further detail
Decision trees can be combined with many other decision tools and help compare likely results between alternative decisions.
Decision trees help distinguish controlled events from uncontrolled events and support best guesses using available information.
★ Must-know
Further detail
List options, branch outcomes, attach probabilities and pay-offs, then compare expected values.
★ Must-know
Cost-benefit analysis requires a comprehensive list of relevant costs and benefits, after which total costs are subtracted from projected benefits or expressed as a ratio.
Direct costs include manufacturing expenses, raw materials, direct manufacturing labour and inventory, while indirect costs include utilities, rent, overheads and electricity.
Further detail
Other relevant costs include competition, regulatory and environmental risks, opportunity costs, and intangible costs such as employee impact, delivery delays, construction and a new business strategy.
Benefits may include competitive advantage, intangible benefits from customer satisfaction and improved employee safety, and increased revenues or sales from a new product or higher production.
★ Must-know
Cost-benefit analysis provides an evidence-based evaluation that reduces personal bias and simplifies complex decisions by expressing them as costs versus benefits.
Cost-benefit analysis is limited because market demand, material costs and the global business environment can be difficult to predict, especially over long periods.
The quality of a cost-benefit analysis depends on the accuracy and completeness of the data used to prepare it.
Further detail
Cost-benefit analysis can reveal hidden indirect or intangible costs and benefits that are not initially obvious.
Cost-benefit analysis is better suited to short- and medium-length projects because long-term forecasts may fail to account accurately for inflation and other changes.
Cost-benefit analysis should not be the only tool used to determine the future direction of a business because moral and human considerations may not be captured by the business case.
★ Must-know
Critical path analysis represents the entire project as a network of smaller activities that are linked according to their dependencies and required completion order.
Critical path analysis helps managers predict project timescales, show how each activity affects later work, and assign appropriate teams or departments to tasks.
Further detail
★ Must-know
Further detail
★ Must-know
Further detail
Working backward from the final activity helps identify the connected line of activities that have no float and therefore must remain on schedule.
In the Hunter Ltd building project, activity A takes 10 weeks, B takes 5 weeks after A, C takes 4 weeks after A, D takes 3 weeks after B, E takes 2 weeks after D, F takes 3 weeks after D, G takes 1 week after E, H takes 6 weeks after C and F, and I takes 2 weeks after G and H.
Map activities, identify dependencies, calculate earliest and latest times, then trace zero-float activities.
★ Must-know
Critical path analysis can reduce delays by involving managers in detailed planning and ensuring that resources are available for activities at the appropriate time.
Critical path analysis can save time by allowing suitable activities to operate simultaneously, while also clarifying dependencies and identifying activities requiring attention.
Critical path analysis may fail when complex activities cannot be represented accurately, activity-time estimates are inaccurate, external factors change, or projects are chaotic and allow frequent changes in duration.
Further detail
Comparison of Decision Techniques
| Technique | Main use | Key strength | Main limitation |
|---|---|---|---|
| Decision tree | Compare choices through probabilistic outcomes | Shows alternatives and possible consequences clearly | Can become complex and depend on unrealistic expectations |
| Cost-benefit analysis | Compare projected costs and benefits | Evidence-based and exposes hidden factors | Forecasts and data may be inaccurate |
| Critical path analysis | Plan project timing and dependencies | Identifies time-critical activities and required resources | Depends on accurate estimates and stable conditions |
Test your knowledge on Business Decision-Making Techniques with 11 multiple-choice questions with detailed corrections.
1. What does a decision tree primarily represent?
2. What is a decision tree primarily used for in decision-making processes?
Memorize the key concepts of Business Decision-Making Techniques with 11 interactive flashcards.
What does a decision tree map?
The possible outcomes of a series of related choices.
Decision tree: Purpose
Map outcomes of choices, compare costs, benefits.
What shape marks a decision point in a decision tree?
A square marks the decision point.